UPDATE, SPRING 2006
North Indian River Inlet Marina
Complex
Delaware Seashore State Park
State Managed Rehabilitation and Modernization
Plan
Status Report
March 2006
Prepared by: W. Britt Murray
Chief, Office of Design & Development
Division of Parks and Recreation
In 1970, the State of Delaware purchased the Indian
River Marina. Major renovations with a lifespan of 15 years were made in
1980 to 1981, and docks and slips were added in 1988. In 1996,
Applied Technology & Management, Inc. (ATM), under contract to the Division of
Parks and Recreation, conducted an engineering study and recommended a
reconstruction plan. There followed several years of unsuccessful attempts
to win state funding, ultimately prompting the Division to develop a
financing plan that utilized a portion of the 21st Century Parks Endowment
Fund. Therefore, reconstruction funds would not come from state taxes or
the General Assembly. The General Assembly directed Parks to implement the
financing plan in 2002.
Throughout 2002 and 2003 a series of meetings kept the
public informed and allowed them to comment on the final design plans. From
the reconstruction recommendations and the public meetings, several issues
rose to the surface; specifically replacement of deteriorated floating
docks, improved electrical services and dredging of the marina basin. The
Division has responded to these concerns and has now completed all
improvements related to these issues as well as many other improvements at
the site.
Safety improvements began in late 2002 and included a
new sidewalk separated from the bulkhead so users will not encounter
sinkholes. The deteriorated portions of the dock were repaired with steel
plates. Work has continued year-round, and has resulted in the completion of
the planned projects through 2005, and is on schedule for 2006 and 2007.
What has evolved from this project is a
state-of-the-art facility that will satisfy the requirements of recreational
and commercial boaters and fishermen, and will provide an enticing vacation
destination year-round. The following is an update on the status of each
of the recommended improvements.
-
DONE: Floating docks
were removed and 274 new wetslips have been built. The new slips are
ADA accessible.
-
DONE: The marina basin
has been dredged to provide five feet of water at low tide.
-
DONE: The public boat
landing has been rebuilt with additional trailer spaces.
-
DONE:
A new drystack storage building with 156
berths and two staging docks has been completed. The staging docks will
accommodate one-third of the drystack storage capacity, and are ADA
accessible (the building is ready
to open pending approval of the fire protection system by the state Fire
Marshall).


Drystack Storage Facility
-
DONE: The fixed concrete
piers have been completed and the new 50-ton travel lift is operational.
-
DONE: Environmental
upgrades to the marine services and drystack areas have been completed,
including sand filters and oil and water separators. These and other
efforts helped IRM become the first
Clean
Marina in Delaware.
-
DONE: New shoreline
protection and stabilization in the form of a steel sheetpile bulkhead
has been installed.
-
DONE: The existing fuel
dock has been replaced with a floating fuel dock with in-slip fueling
for charter boats. The fuel and charter dock is ADA accessible.

Improved Floating Fuel Dock
-
DONE: Additional parking
and storm water improvements have been completed.
-
DONE: Twelve ADA
accessible cottages have been built along the inlet with associated
parking and storm water management improvements.
-
SOON TO BE COMPLETED: The
construction of the Dry Stack Storage facility has been completed. Once
the new 440,000 gallon water storage tank is finished and operational,
the fire protection system installed in the Dry Stack Building can be
tested and placed into operation. We anticipate the facility to be open
to the public in the Spring of 2006.
Work has just begun on the new
Restrooms/Ships’ Store located near the marine Service Area. This building
should be completed by July 2006.
Further improvements are scheduled for 2006 and
2007. These include renovation of the Operations Building with a restroom
and shower suite for slipholders; a new Sundries Store; and an upgraded
administrations facility. The current fish cleaning/ bait and tackle shop
will be renovated. The Park Office has been relocated next to the restored
historic Indian River Life-Saving Station. Portions of the campground remain
closed due to the reconstruction of the Indian River Inlet Bridge and will
be reopened when construction allows. |